Dredging Operations

Lake Update

As previously communicated, the odor at the south end of the lake has been attributed to low oxygen levels. Due to this, we have reached out to property owners at the south end for their assistance utilizing a series of aerators to help with this oxygenation problem. Additionally, we have temporarily suspended our dredging operations in the south end. Continuing to dredge while the lake water is in an anaerobic state can further harm the health of the lake, and inhibit the restoration chances.

For this reason, we have temporarily moved our dredging operation to the north end of the lake where the oxygen levels are better to minimize dredging downtime. We will reevaluate the south end in 2 weeks to see if the oxygen levels improve and we can resume dredging at the south end.

We know this is frustrating and appreciate your patience.

History of Concerns About Water Quality, Erosion, or Dam Safety 1966-2016

RRA Member Carolyn Tharp compiled a report on lake management to highlight moments during the first 50 years of The Shores when lake management and concerns were mentioned. This report was approved to be posted here on the website at the Sept 5th meeting of the Board of Directors. It is linked below and is also listed under LMC Reports on our Lake Management pages.

Dredging Update

Dredging is progressing along the southwest channel of the south end of the lake.

The equipment hit the water right after the pools opened for the season and already over 400 loads of sediment have been removed from the lake. Our plan is to start attacking the southeast channel when work is completed on the southwest channel. Aside from a few mechanical breakdowns with the push-boat and general maintenance to the scows, everything has been going smoothly.

The channel is now open from R.L. 21 to Lot 1116.

Dredging Advisory Committee

By: Dawn Longo

For several years, there has been discussion around dredging the lake at Roaming Shores. Even though we have been removing sediment for the last three years to ensure the health of the largest privately owned lake in the state of Ohio  residents were interested in improving the efficiency of the endeavor and speeding up the process. Dan Mullins and  his team have done a great job but dredging is only part time for them – they still open the pools, cut the grass, make repairs, etc.  

In order to capitalize on the ideas and suggestion of the membership at the monthly association meetings and the annual Board meeting, the RRA board organized a working “Dredging Advisory Sub-Committee” to hold active, meaningful discussions to plan and help improve our dredging activities. A major portion of these discussions will deal with existing practices, potentially new practices, current funding limitations, and future funding potentials.

The public was invited to a meeting on Saturday, November 24, 2018 at the clubhouse as an informational session and members were asked to sign up for the committee.

The following association members signed up:

Jim Fell, Dawn Longo, Mike Petersen, Theresa Ankuda, Denny Crandall, Gerry Dixon, Terri Freeland, Fred Jenkin, Rick Brothers, Dan Mullins, Jack McMillin, Jim Swartz, Louise Lisac and Howard Tuttle.

The committee had their first meeting January 12, 2019 and split into four separate sub-committees as follows.

Committee #1 is Jack McMillin, Jim Swartz and Louise Lisac with Dan Mullins. They will investigate expanding the current operations.

Committee #2 is Jim Fell, Gerry Dixon, Dawn Longo and Chris Lisac. They will investigate creating a parallel operation.

Committee #3 is Denny Crandall, Ankudas, Terri Freeland and the Jenkins. They will investigate dredging by an outside contractor. Their scope was expanded to include inquiring as to whether any of these contractors are available for hire by individual property owners.

Committee #4 is a Water Flow Control Group which will be an ongoing committee to ensure proper maintenance of the lake. These members will not remain on it indefinitely. They were tasked with documenting processes and procedures that are vital to proper maintenance of the lake so dredging does not become a major issue again. Members are Louise Lisac, Rick Brothers, Mike Petersen and Howard Tuttle.

Each team was asked to present their findings at the next meeting scheduled for February 9, 2019.

The committee met on February 9th and each team came back with valuable information as summarized below:

Team # 1 Update: They haven’t gotten as far as they would like with their plan but they did note that 2 temporary workers have already notified them that they will not be coming back this summer. We typically hire 7 seasonal employees. Jobs will be posted but if you know people looking for summer employment send them Dan’s way.

Team #2 Update: Presentation was given for a parallel operation with costs associated for removing 12,000 cubic yards of additional sediment. Since 6,000 cubic yards are taken out each season the number 12,000 was used to gather quotes. See Team #3 updates as quotes may be firmer with that information. Will send an electronic copy of their presentation to board members.

Team # 3Update: A company was found that can provide us with a bathymetric survey which could help us determine how many cubic yards need to be removed from the lake. This number will be extremely helpful for all teams. The cost for this work is $5,300 but we don’t need Survey Area #1 (across the bridge) so the total would be $630 less. If we were to obtain any additional services from them, this fee would be deducted from the fees for that  additional work. Any expenditure of this type would need to be approved by the board who meets again on February 21. This committee is going to contact others who may provide the same type of service as well.

Team #4 Update: One of the options that has been brought up in the past is siphoning. This committee determined that siphoning is not an option. They also investigated the possibility of increasing the size of the current valve at the dam. A 2010 study done by CT Consultants out of Mentor found it impractical and that is still the case.  One thing the committee suggested was to consider an earlier drawdown. This would have to be communicated early and we would have to be sure that equipment and manpower are available to utilize a lowered lake for aggressive dredging.

Also, just a reminder to association members the association owns the lake while the village owns the dam.

These are all still a work in process so don’t assume that the lake will be lowered earlier this year or anything that you’ve seen above.

The committee is moving forward and some of the next steps are:

Begin a communications campaign to keep citizens abreast of progress. It is important that everyone in the association be aware of the work being done and the progress being made. If anyone has any constructive comments to bring to light please feel free to share them with anyone on the committees. You can send these comments to the e-mail address of it@roamingshores.org

 The association will post a public notice in the newspaper requesting anyone interested in submitting a quote/proposal for dredging to do so by February 28th so the committee can review on March 2nd.  Companies will then be contacted to come in to present and answer any questions regarding their quotes.

Of course, there will be dollars involved with any project of this magnitude. The quotes will allow the committees  to provide members a feel for what those dollars might be and how those funds will be obtained. It is important that every member of the association pay their annual dues and suggest the same to their neighbors. Unpaid dues are an entirely different topic but will be addressed more aggressively in 2019.

The committee hopes to be able to give an update at the annual meeting on April 27, 2019.

Dredging Advisory Board Meeting to be Rescheduled

Please note that the Dredging Advisory Board meeting that was scheduled for November 3rd will be rescheduled. The Board will decide on a new date at their meeting this week on November 1st at 7:30pm in the Clubhouse.

Informational Dredging Presentation August 25th

The RRA Board of Directors and Operations Manager will be hosting an informational Dredging Presentation at the Clubhouse on Saturday, August 25th at 10am. Please join us to learn details about our dredging program.

Prepping for the 2017 Dredging Operation

Once the road ban was lifted this year, the RRA maintenance crew got to work on dredging for the year. The first step is to move the dried sediment from last year’s operation. Over 6000 cubic yards of sediment was removed last year alone. It is transported to the dewatering site where it dries out over the winter and is ready to move and collect by May. See pictures below of the dirt being moved to get a feel for just how much sediment was removed from our lake.

During the dredging operation over the summer the maintenance crew will use the bulldozer to keep spreading material as it is removed from the lake.

Top soil from this operation is made available to our Members free of charge. It is located next to our cinder bay behind the old maintenance garage near the RRA Office and on the RL Lot near Knowlton Entrance on Morning Star Dr.

2016 Dredge Operation Summary

Prepared by: Dan Mullins, Operations Manager

The 2016 dredging operation began April 16 right after the road band was lifted. The maintenance crew had the task of consolidating the material that was taken from the lake in 2015 to the dewatering site that was now dry enough for recollection, pictured below.

This task took approximately two weeks to complete, and involved using our bulldozer to re-pile the approximate 5700 yards of dewatered material. During the dredging operation over the summer the maintenance crew uses the bulldozer to keep spreading material as it is removed from the lake.

The dredging barges were launched at the beginning of the month of May. The maintenance crew moved the barges to Fishermen’s Cove to begin dredging where they had left off last season. Material began being removed from Fishermen’s Cove beginning May 18. The dredging operation continued in Fishermen’s Cove through mid June where another approximate 2500 yards had been removed from the lake. At this point the maintenance crew also had to start preparing for the summer activities and having the amenities ready for the season.

Utilizing our summer help to take care of most of the day-to-day work, general cleanup, trash removal and lawn maintenance allowed us to concentrate on our next area to dredge which was Nature’s Cove. A previous silt pond that was installed in the end of this cove had failed and blown out. This cove is the main inlet for a large agricultural farm on the west side of the lake. From mid June through mid July the maintenance crew removed approximately 1550 yards of material from Nature’s Cove.

Nature’s Cove

The dredging operation continued in July along with the preparation for our summer activities, 4th of July, and our 50th anniversary. It was a very busy summer. With Nature’s Cove complete, the dredging operation then moved to Sugar Creek Cove. Next to the south end of the lake, Sugar Creek Cove had the next significant amount of silt build up and was identified as a cove that has the most boat docks that are unusable due to silt build-up.

A staging area or take out point was installed at the inlet of this cove. The maintenance crew did try to remove material from the inlet of this Cove from land in December 2015 but was unsuccessful due to high water. A staging area or take out point was installed at the mouth of Sugar Creek near beach #2. This staging area had to be installed from land as it was too shallow to do from the water. This takeout point in Sugar Creek will now cut our turnaround time by two thirds. The dredging crew will return to Sugarcreek and keep dredging the south channel up to the takeout point at the east end inlet of this cove. The staging area at beach #2 will be used in 2017 as a takeout point for the fastest turnaround in this cove. The amount of material removed from Sugar Creek last year was approximately 2490 yards.

Below is a map of the lake showing the areas marked that have been dredged:

Looking forward to 2017, we will begin dredging in Sugar Creek. Our turnaround time in 2017 versus 2016 will be much faster with the addition of the staging area/takeout point added at beach 2. This will be a significant improvement in offloading the material. The amount of material still needing to be removed from Sugar Creek will determine the dredge operation for the season.

In conclusion, overall the 2016 dredging operation went very well removing 6,300 yards of material from the lake, fuel cost diagram below:

I would like to add the maintenance crew continuously looks for improvements to increase our efficiency for the dredging operation. I am also pleased to report for the 2016 season there were no injuries involved with the dredging operation or damage to any of the equipment. Within the maintenance department safety is our number one priority on all of the projects and tasks done here at Roaming Shores.

I would also like to mention that many residents took advantage of the topsoil and fill dirt that was made available to the residents free of charge that was located at the maintenance garage. Some residents came to pick up truckloads of material and other residents came with just a 5 gallon bucket to be filled. That service will be available again this year. We will keep material stored this season again at the maintenance garage free of charge for the association members. Looking forward to a successful 2017 season!

2015 Dredge Operation Summary

By: Dan Mullins
RRA Operations Manager

Operation for the season began April 16th, the day after the road weight limit ban ended. Our first task was to prepare the dewatering site which involved stock piling the material from 2014 to make room for the incoming material from 2015. This task was incorporated into the regular duties of the maintenance department along with the spring clean up from the previous winter, roadside clean up’s, downed tree limbs and pot-hole repairs, both pools had to be opened, beach clean ups, buoys installed on the lake, volley ball and tennis courts all had to be ready before Memorial Day, the start of the summer season. These tasks continued through April and May. During this time period, one of our full-time employees went out on a medical leave for most of the 2015 dredge & summer season. This loss of 25% of our manpower was a big setback, but adjustments were made and we moved forward.

D1

The staging area at Fishermans Cove was installed, pictured below, and the work at our dewatering site continued. This staging area was a challenge due to the heavy amount of silt in this cove. The barges were launched and the dredge crew finished a channel at the end of Plum Creek removing 90 yards from this cove. The dredge crew then moved to the small, unnamed cove, on the northeast side of the lake. This cove was cleaned out removing 150 yards of material to assist with road drainage on Morningstar. The dredge crew then headed to Fishermans Cove. On the way towards Fishermans Cove, a call came into the office that a very large tree had fallen into the lake at the mouth of Plum Creek. The maintenance crew was able to utilize the excavator and barges to remove this very large oak tree from the water. The dredging platform made this task safer and decreased the amount of time it usually would take to remove this type of obstacle. Prior to having the dredge platform to work from in the water, tree’s this size would take on average 2 to 3 days cutting pieces small enough to handle safely from a boat to remove. The tree in the below photo took 3 hours to remove from the lake. This versatility allows us to remove these types of obstacles from the lake in a safer and more efficient manner.

D2

D3

Material being removed from the lake moved into high gear on June 17th. The access to Fishermans Cove was finished and the dredge crew, in between keeping all of the other summer amenities maintained, began dredging. For the month of June, 8 days were spent on the water dredging and 550 yards of material was removed from Fishermans Cove.

July was a busy month with the Fourth of July Fireworks and all of the other summer activities going on. Maintenance of the dewatering site, and access drives continued daily, pictured below. Another large tree was removed from Island Cove. The barge platform again made this task safer and allowed us to return to dredging the next day to Fishermans Cove. Along with their regular summer duties, the dredge crew spent 11 days on the water and removed 550 yards of material from Fisherman’s Cove.

D4

The month of August was the end for all but 2 part time summer employees. This kept the full-time crew focusing on amenities and the winding down of the summer season. The crew dredged on the water a total of 9 days for the month of August and removed 550 yards of additional material from Fisherman’s Cove.

With the pools closing in September and the slowing of the need for grass mowing this allowed the dredge crew to remove 1,000 yards of material in Fishermans Cove in 10 days time. Our full-time employee returned to work on light duty, this had a positive impact on our production.

The month of October proved to be the most productive dredging month. This was due to manpower strictly focused on dredging. They were dredging daily for almost the entire month and removed an impressive 2,900 yards in 18 days. The weather was unusually dry and this allowed us to maintain our dewatering site easily in a month that is normally rainy and cold. Before and after pictures of Fishermans Cove below:

D5

D6

The barges were removed from the lake the last week of October before the lake draw down on November 2nd. There was the intention to continue dredging from the shore if the lake draw down was sufficient enough to allow this, unfortunately the cycle of drawn down did not allow us this opportunity.

Overview – The 2015 season total of removed material from the lake was 5,790 yards. We used 255 gallons of off road diesel and 193 gallons of on-road diesel. Our bulldozer consumed 65 gallons of off-road diesel for the season and our push-boat used 35 gallons of regular gas. We are very pleased with the performance of our equipment. We had no mechanical breakdowns in the 2015 dredge season. With this being our first full year incorporating the dredging operation along with the regular duties of the maintenance department, I am calling this season a great success!

Moving forward in 2016, the dredge crew continues to improve on the knowledge gained and improving the process. The dredging schedule for 2016 will be to finish Fishermans Cove, then move to Nature’s Cove and then onto Sugarcreek.

We are planning for another successful season in 2016!

E-Mail Blast Sign-Up
email-blast




    Roaming Shores E-Blast Categories

  • Weekly Newsletter
  • Emergency & Lake Alerts
  • Meeting Updates/Changes

View previous campaigns.