Lake Depth Improvement Sub-Committee Update
Equipment average hauling weight:
- #1 Truck: Chevy 1 ton – 4,000lbs
- #2 Truck: Chevy C6500 – 12,000lbs
- #3 Truck: Mac Dumptruck – 32,000lbs
Phase 1 of Dredging is completed.
Phase 2 Report Update:
Equipment Purchased:
- One Mac Truck: Completed – Budgeted $20k, Actual $15k
- One Trailer: Completed – Budgeted $6,500, Actual $3,500
- Two John Deere Trackhoes : Completed – Budgeted $28k each, Actual $22,700 each
- Two Trackhoe Buckets: Completed – Budgeted $3,700k each, Actual $3,500 each
Bids Completed:
- One spud barge 24” x 40”: Completed – Budgeted $62k, Actual $49,745.47
Current Bids Out:
- Three hopper barges 12” x 24”
- 2 are out for bid at this time, Budgeted $28k each
- One boat motor 60hp
- Out for bid, Budgeted $8,200
Sediment Testing:
525 cubic yards have been taken out of 7 coves. This was for testing purposes to see how fast new sediment comes into the Lake.
Phase 3 of Dredging is targeted to begin in the middle of July 2014 or sooner.
Next Workshop: Saturday, January 25th @ 10am at the Clubhouse.