Dredging Operations

Dredging Update

8-15-14-dredge

Progress continued on the barges to be used for dredging this week as one of our excavators has been successfully loaded onto the spud barge. The barge had to first be prepared for the excavator by adding lumber to its deck and to its sides to prevent damage.

We understand your anxiousness to begin dredging, but rest assured that we’re drawing closer every day. There are still steps to go through on the dredge equipment itself and with several government agencies to make sure that we are in compliance with the rules that they have set forward to protect the lake and the environment. In addition, we still have our day-to-day maintenance projects (pools, mowing, culvert, etc.) to complete in-between. It takes time, but it’s moving forward.

Dredging Update

Things are moving forward with equipment needed for dredging the lake. The spud barge and dump scowl are being fabricated by Lake Erie Ship Repair and Fabrication. Check out the pictures of the progress. Work should be completed by Mid-July with dredging to begin shortly thereafter.

Spud Barge

Spud Barge

Dump Scowl

Dump Scowl

In house, our crew constructed a push boat which will be used to move the dump scowls from the spud barge to the shore to be emptied. The push boat was launched and tested last week with no issues.

Push Boat

Push Boat

Lake Depth Improvement Sub-Committee Update

Equipment average hauling weight:

  • #1 Truck: Chevy 1 ton – 4,000lbs
  • #2 Truck: Chevy C6500 – 12,000lbs
  • #3 Truck: Mac Dumptruck – 32,000lbs

Phase 1 of Dredging is completed.

Phase 2 Report Update:

Equipment Purchased:

  • One Mac Truck: Completed – Budgeted $20k, Actual $15k
  • One Trailer: Completed – Budgeted $6,500, Actual $3,500
  • Two John Deere Trackhoes : Completed – Budgeted $28k each, Actual $22,700 each
  • Two Trackhoe Buckets: Completed – Budgeted $3,700k each, Actual $3,500 each

Bids Completed:

  • One spud barge 24” x 40”: Completed –  Budgeted $62k, Actual $49,745.47

spud-barge500px

 

Current Bids Out:

  • Three hopper barges 12” x 24”
    • 2 are out for bid at this time, Budgeted $28k each
  • One boat motor 60hp
    • Out for bid, Budgeted $8,200

Sediment Testing:

525 cubic yards have been taken out of 7 coves. This was for testing purposes to see how fast new sediment comes into the Lake.

Phase 3 of Dredging is targeted to begin in the middle of July 2014 or sooner.

Next Workshop: Saturday, January 25th @ 10am at the Clubhouse.

Lake Depth Improvement Sub-Committee – Phase 1 Report

Phase 1 Report:

Preliminary Dredging Meetings

  • May
    • Grand Lake St. Marys: Shallow water State Lake in western Ohio currently undergoing a massive hydraulic dredging operation. Started in 1964.
    • Lake Lakengren: Private lake association in western Ohio currently undergoing a mechanical dredging operation. Met during OLCA (Ohio Lake Communities Association) conference.
  • June
    • Army Corp of Engineers: Met to learn which permits would be required for dredging.
    • EPA: Met to discuss dredging.
    • ODNR: Met to discuss dredging.
    • Roaming Shores Village: Met to acquire permits for Dredge Material Disposal Site.
  • July
    • Chagrin Valley Engineers: Designers for Dredge Material Disposal Site.
    • Ashtabula County Water & Soil Dept.: Met to learn rules regarding settlement ponds and Dredge Material Disposal Site.
  • August
    • EnviroScience: Performed depth study for dredging locations. Will use information from 2009 study which cost over $20,000 to perform.
    • Chagrin Valley Engineers: Plans finalized for Dredge Material Disposal Site.
    • ODNR: Registered for permission to build Dredge Material Disposal Site.
  • September
    • ODNR: Paid for permits.

This Dredging project will not increase Dues & Assessments any further. The project can completed without the need to take out a loan from the bank.

Phase 2 report will be in the December Edition of the Shores News.

Lake Depth Improvement Sub-Committee Meeting Minutes – June 18, 2013

Members present include Ron Morris, John Ball, Jim Schwartz, Mike Ritter, and Chairman Ed Baitt.

Meeting called to order at 7:30PM at the RRA Clubhouse.

Items discussed:
1. Need to obtain a mechanical scoop-dredging rig similar in design to the one currently used at Lake Lakengren. The rig should be owned by the RRA since the ability to lower the lake level via a siphon spillway is still at least a year or more off and it will be used over the equipment’s lifetime. Use of this rig does not require the lake level to be lowered so dredging can begin as soon as it is in place. Other equipment can be used when the lake level can be controlled. The dredging rig would include 2 backhoes, 1 truck, 3 hopper barges, and 1 spud barge and would cost an estimated $200,000. Our own workboat can be used but will need a motor upgrade to a 60hp 4-stroke Mercury outboard motor. A bid was received and reviewed from B&R Construction, Inc. for building the spud barge.
2. The committee intends to dredge only the channel of each cove to allow property owners the ability they once had to boat to the main body of water. Accordingly, the committee will scoop out sediment from the channel near the back of several coves to learn how long it would take for the sediment to return. This may give us an idea of how often the coves channel would need to be dredged. RL50 and RL54 will be sample dredged first.

Meeting was adjourned at 9:15PM

E-Mail Blast Sign-Up
email-blast




    Roaming Shores E-Blast Categories

  • Weekly Newsletter
  • Emergency Alerts
  • Meeting Updates/Changes

View previous campaigns.

Like Us on Facebook
Roaming Shores, OH
October 18, 2018, 6:02 am
Clear
Clear
36°F
real feel: 28°F
current pressure: 30 in
humidity: 74%
wind speed: 11 mph NW
wind gusts: 13 mph
sunrise: 7:39 am
sunset: 6:37 pm
Forecast October 18, 2018
day
Mostly sunny
Mostly sunny
49°F
Forecast October 19, 2018
day
Intermittent clouds
Intermittent clouds
59°F
Forecast October 20, 2018
day
Mostly cloudy with showers
Mostly cloudy with showers
52°F