Next Stage for Dredging: Fisherman’s Cove

With our crew becoming more acclimated to the new dredging equipment in Plum Creek, plans are moving forward to begin digging in Fisherman’s cove. This cove was determined to have the most sedimentation, according to a study by Enviroscience. In order to remove spoils from this problem area efficiently, our crew put in a 350ft access road, the process only took a couple of days.